Today’s designs
have many functional as well as test modes. A number of clocks propagate to
different parts of design in different modes. And a number of control signals
are there which control these clocks. These signals are behind switching on and off the
design. Let us say, we have a simple design as shown in the figure below. Pin
‘SEL’ selects between two clocks. Also, ‘EN’ selects if clock will be
propagating to the sub-design or not. Similarly, there are signals that decide
what, when, where and how for propagation of clocks. Some of these controlling
signals may be static while some of these might be dynamic. Even with all this,
these signals should not play with waveform of the clock; i.e. these should not
cause any glitch in clock path. There are both architectural as well as timing
care-abouts that are to be taken care of while designing for signals toggling in
clock paths. This scenario is widely known as ‘clock gating’. The timing checks
that need to be modeled in timing constraints are known as ‘clock gating
checks’.
Figure
1: A simplest clocking
structure
|
Definition of clock gating check: A clock gating check is a constraint, either applied or inferred automatically by tool, that ensures that the clock will propagate without any glitch through the gate.
Types of clock gating checks: Fundamentally, all clock gating checks can be categorized into two types:
Types of clock gating checks: Fundamentally, all clock gating checks can be categorized into two types:
Figure 2: AND type clock gating check; EN signal controlling CLK_IN through AND gate |
Figure
3: Clock being clipped when
‘EN’ changes when ‘CLK_IN’ is high
|
Figure
4: Clock waveform not being
altered when ‘EN’ changes when ‘CLK_IN’ is low
|
Theoretically,
‘EN’ can launch from either positive edge-triggered or negative edge-triggered
flops. In case ‘EN’ is launched by a positive edge-triggered flop, the setup
and hold checks will be as shown in figure 5. As shown, setup check in this
case is on the next positive edge and hold check is on next negative edge.
However, the ratio of maximum and minimum delays of cells in extreme operating
conditions may be as high as 3. So, architecturally, this situation is not
possible to guarantee the clock to pass under all conditions.
Figure
5: Clock gating setup and hold
checks on AND gate when 'EN' launches from a positive edge-triggered flip-flop
|
On the contrary,
if ‘EN’ launches from a negative edge-triggered flip-flop, setup check are
formed with respect to the next rising edge and hold check is on the same
falling edge (zero-cycle) as that of the launch edge. The same is shown in figure 6. Since,
in this case, hold check is 0 cycle, both the checks are possible to be met for
all operating conditions; hence, this solution will guarantee the clock to pass
under all operating condition provided the setup check is met for worst case
condition. The inactive clock state, as evident, in this case, is '0'.
Figure
6: Clock gating setup and hold
checks on AND gate when ‘EN’ launches from negative edge-triggered flip-flop
|
|
Figure 7: An OR gate controlling a
clock signal 'CLK_IN'
|
Figure
8: Clock being clipped when
'EN' changes when 'CLK_IN' is low
|
Figure
9: Clock waveform not being
altered when 'EN' changes when 'CLK_IN' is low
|
As in case of
AND gate, here also, ‘EN’ can launch from either positive or negative edge
flops. In case ‘EN’ launches from negative edge-triggered flop, the setup and
hold checks will be as shown in the figure 10. The setup check is on the next
negative edge and hold check is on the next positive edge. As discussed earlier, it cannot guarantee
the glitch less propagation of clock.
Figure
10: Clock gating setup and hold
checks on OR gate when ‘EN’ launches from negative edge-triggered flip-flop
|
If ‘EN’ launches
from a positive edge-triggered flip-flop, setup check is with respect to next
falling edge and hold check is on the same rising edge as that of the launch
edge. The same is shown in figure 11. Since, the hold check is 0 cycle, both
setup and hold checks are guaranteed to be met under all operating conditions
provided the path has been optimized to meet setup check for worst case condition. The inactive clock state, evidently, in this case, is '1'.
|
We have, thus
far, discussed two fundamental types of clock gating checks. There may be
complex combinational cells other than 2-input AND or OR gates. However, for
these cells, too, the checks we have to meet between the clock and enable pins
will be of the above two types only. If the enable can change during low phase
of the clock only, it is said to be AND type clock gating check and vice-versa.
SDC command for application of clock gating checks: In STA, clock gating checks can be applied with the help of SDC command set_clock_gating_check.
SDC command for application of clock gating checks: In STA, clock gating checks can be applied with the help of SDC command set_clock_gating_check.